Projects

Naval Branch Health Clinic, Gulfport MS

  • Scheduling and Monitoring of Project Completion for Surety
  • Delay and Damages assessment for Surety

Chemistry and Chemical Biology Building, Rutgers University, NJ

  • $90,000,000 new facility with auditoriums, labs, classrooms and offices
  • Evaluation of termination for default of general contractor on behalf of architect
  • Assessment of Delay Damages

United States Supreme Court, Washington, D.C.

  • $3,000,000 restoration of courthouse facade
  • Evaluation of subcontractor termination for default on behalf of surety
  • Issue expert report and present findings in successful mediation leading to withdrawal of bond claim and conversion to termination for convenience

Kingsboro Addiction Center, Brooklyn, NY

  • $5,000,000 rehabilitation of an existing, operating facility
  • Evaluation of defaulted contractor’s claims on behalf of surety
  • Issue expert report supporting contractor’s delay claims on behalf of completing surety

McKeesport Waste Water Treatment Plant

  • Monitoring of Project Completion for Surety
  • Delay and Damages assessment for Surety

South Middleton Waste Water Treatment Plant

  • Monitoring of Project Completion for Surety
  • Delay and Damages assessment for Surety

Kiski Waste Water Treatment Plant

  • Monitoring of Project Completion for Surety
  • Delay and Damages assessment for Surety

34 East 51st Street New York, NY

  • $70,000,000 Midtown Manhattan office tower
  • Evaluation of contractor’s foundation delay claim against owner
  • Issued rebuttal expert report addressing contractor’s foundation delay claim and quantifying contractor’s responsibility for schedule delays
  • Testified on behalf of owner in American Arbitration Association hearings

World Trade Center Tower 1, New York, NY

  • $12,000,000 Fire Protection System for World Trade Center Tower 1
  • Evaluation of Hurricane Sandy related damage to work in place, subsequent delay impacts and monetary damages incurred by subcontractor
  • Issued expert report used by subcontractor to negotiate a settlement with Port Authority of New York & New Jersey

World Trade Center Transportation Hub, New York, NY

  • $330,000,000 subcontract to fabricate and install structural steel, metal deck and precast concrete
  • Evaluation of Hurricane Sandy related delays, impacts to erection productivity and quantification of related costs
  • Issued expert report and presented findings supporting subcontractor’s claims ahead of settlement with Port Authority of New York & New Jersey

RTD Eagle P3, Denver, CO

  • $2,700,000,000 commuter light rail connecting Denver International Airport, Coors Field, Denver Union Station, and suburbs north of Denver
  • Evaluated contractor’s request for change order
  • Support negotiation of a change order with owner through development of delay mitigation scenarios reducing schedule and cost impacts

Doty Hall Renovation

  • $25,000,000 renovation of existing Geneseo Campus Building
  • Delay and Damages analysis for surety

Staten Island Courthouse, Staten Island, NY

  • $9,000,000 curtainwall subcontract
  • Evaluation of defaulted subcontractor’s claims on behalf of surety
  • Issued expert report and presented findings supporting subcontractor’s claims during negotiations resulting in settlement

Fore River Bridge Replacement, Quincy, MA

  • $250,000,000 four lane, twin tower, lift span bridge and associated dolphins, fenders, abutments, and approaches
  • Developed a resource, cost loaded baseline CPM construction schedule

Denver Transit Partners Change Order Development

  • $2 Billion construction of Light Commuter Rail in Denver Colorado
  • Assist Project Team in Schedule Analysis for $100,000,000 Change Order Proposals

Route 337 Hampton Blvd Modifications

  • $40,000,000 construction of depressed roadway and relocation of utilities
  • Evaluation of contractor schedule analysis and claims for surety

United States Embassy to the United Nations, New York, NY

  • $110,000,000 construction of 27 story “hardened” US Government office building adjacent the United Nations building
  • Evaluation of defaulted subcontractor’s claims on behalf of surety
  • Issued expert report used in settlement negotiations

Quad Student Housing, Phase 2, Old Dominion University

  • $11,000,000 Dormitory Facility
  • Preparation of Change Order Request for surety and contractor

130 Liberty Street Deconstruction, New York, New York

  • $350,000,000 abatement and deconstruction of a 41-story office building within the World Trade Center site
  • On site progress, cost, schedule, and claims monitoring on behalf of surety
  • Issued expert report and rebuttal report addressing scope and bids
  • Deposed in matter before Supreme Court of the State of New York, County of New York

Pier A Core and Shell Renovation, New York, NY

  • $30,000,000 New York City financed renovation of historic waterfront pier on southern tip of Manhatta
  • Analyzed electrical subcontractor’s claims of schedule delay and damages
  • Issued expert report and presented findings during mediation with owner

Payton Lane Nursing Home, Southampton, NY

  • $30,000,000 HUD financed nursing home construction
  • Analyzed schedule delays and damages on behalf of surety
  • Issued expert report quantifying delay and impact costs
  • Testified before United States District Court, Eastern District of New York

Flushing Avenue Reconstruction, Brooklyn, NY

  • $53,000,000 water distribution and streetscape enhancement project for the NYC Department of Design and Construction
  • Analyzed delay claims of defaulted contractor on behalf of surety
  • Issued expert report and presented findings during settlement negotiations

Sigma Construction, Brooklyn, NY

  • $8,500,000 HUD sponsored building and apartment rehabilitation
  • Analyzed issues surrounding termination for cause
  • Issued expert report in support of contractor’s claims
  • Testified before American Arbitration Association

Islip Airport, Long Island, NY

  • $82,000,000 airport expansion of existing terminal and apron
  • Evaluated owner claim for $15,000,000 apron replacement
  • Developed presentation for mediation that resulted in settlement

972 Kent Avenue, Brooklyn, NY

  • $9,000,000 warehouse conversion to apartments
  • Analyzed issues leading to termination for convenience
  • Issued expert report and presented findings during negotiations resulting in settlement

Kings County Hospital Renovations, Building E, Brooklyn, NY

  • $8,000,000 Existing Hospital Electrical Renovation
  • Evaluated issues surrounding contractor’s extra work claim
  • Issued expert report supporting extra work claims
  • Presented finding during negotiations resulting in settlement

Griffith Water Treatment Plant, Fairfax, VA

  • $200,000,000 Water Treatment Plant
  • Analyzed contractor default on behalf of completing suret
  • Issued expert report evaluating delay and disruption claims
  • Presented finding during negotiations resulting in settlement

Goldstein School, Long Island, NY

  • $90,000,000 School Construction Project
  • Analyzed delay and disruption claims
  • Issued expert report supporting contractor’s delay and disruption claims
  • Presented findings during negotiations resulting in settlement

Bronxville School Renovations, Bronxville, NY

  • $30,000,000 classroom, cafeteria, and gymnasium renovation
  • Analyzed issues leading to contractor termination for cause
  • Issued expert report supporting contractor’s claim of wrongful termination
  • Deposed in matter before United States District Court, Southern District of New York prior to settlement

The College of New Jersey, Trenton, NJ

  • $27,000,000 Dormitory Construction Project
  • Analyzed issues leading to contractor’s termination for cause
  • Issued expert report supporting claim of wrongful termination
  • Presented findings to owner during negotiations resulting in settlemen

University of Connecticut, Storrs, CT

  • $35,000,000 Biology/Physics Building
  • Issued expert report supporting contractor’s wrongful termination claim
  • Testified before American Arbitration Association panel

University of North Carolina - Wilmington, Wilmington, NC

  • $160,000,000 bond-funded construction program master plan
  • Issued progress/budget reports for NC Legislative Oversight Committee
  • Maintained master project schedule for entire construction program
  • Developed and maintained program-wide cost forecasting for University and NC Legislative Oversight Committee
  • Analyzed claims and led settlement negotiations

Shore Club Hotel, Miami, FL

  • $100,000,000 renovation of historic South Beach hotel
  • Evaluated issues leading to contractor’s termination for cause
  • Issued expert report supporting claim of wrongful termination
  • Presented findings during negotiations resulting in settlement

Pope AFB Dormitory Complex, Fayetteville, NC

  • $15,000,000 dormitory construction project for US Corps Of Engineers
  • Evaluated issues leading to contractor’s termination for cause
  • Issued expert report supporting claim of wrongful termination
  • Presented findings during negotiations with US Army Corps of Engineer

Logan International Airport Tunnels/Viaducts, Boston, MA

  • $120,000,000 roadway project for Massachusetts Port Authority
  • Issued expert report supporting contractor’s delay, disruption, and loss of productivity claims
  • Presented findings to Massport during negotiations resulting in settlement

Logan International Airport Terminal Area Roadways, Boston, MA

  • Expert Report Supporting Contractor's Delay/Disruption Claim on $100,000,000 Renovation Project
  • Successful Negotiations with The Central Artery

Terrell Prison, Livingston TX

  • $20,000,000 construction of maximum security prison
  • Developed and updated a CPM schedule supporting expedited construction of prison pursuant to court order addressing prison overcrowding
  • Issued compliance reports for Texas Department of Prisons

Detroit Water and Sewer District Controls Automation, Detroit, MI

  • $150,000,000 controls automation project
  • Served as changes/claims coordinator
  • Responsible for preparation and of all time extensions, changes and claims
  • Negotiated directly with owner to set change order amounts and settle claims and time extension requests

Poughkeepsie Municipal Building, Poughkeepsie, NY

  • $15,000,000 renovation of existing municipal building
  • Analyzed contractor delay and disruption claims
  • Issued expert report supporting contractor’s claim

Automated People Mover, Newark International Airport, Newark, NJ

  • $15,000,000 monorail train project linking terminals
  • Analyzed delay and change order entitlement
  • Issued expert report supporting contractor’s claims for extras • Presented findings during negotiations with Port Authority of New York & New Jersey

Acosta Bridge, Jacksonville, FL

  • $40,000,000 slip-form, segmental box girder bridge over the St. John’s River for the Florida Department of Transportation
  • Developed and maintained a cost and resource loaded CPM schedule
  • Developed and negotiated change orders with the FDOT
  • Monitored cost as well as all submittal, change, and notice documents
  • Conducted training seminars on scheduling, delays, changes, claims, and negotiations for FDOT

Fairfax County Government Center, Fairfax, VA

  • $175,000,000 mixed-use construction and land development project
  • Developed cost and resource loaded CPM schedule
  • Issued monthly payment requisitions directly from CPM schedule updates
  • Implemented and maintained electronic document control system tracking all project submittals, requests for information, bulletins, meeting minutes, changes, claims, time extension requests, and correspondence
  • Negotiated change orders and time extensions with owner
  • Developed and maintained cash flow forecasts for contractor/developer

Shinnecock Bay Bridge, Long Island, NY

  • $35,000,000 pile supported bridge and approaches
  • Analyzed contractor’s delay and disruption claims
  • Issued expert report and presented findings to State of New York DOT
  • Deposed before Court Of Claims State of NY ahead of settlement

Shoreham Nuclear Power Plant, Long Island, NY

  • Renovation of existing, operating power plant
  • Analyzed contractor’s delay and disruption claims
  • Identified key documents supporting contractor claims and prepared exhibits and demonstrative graphics
  • Provided litigation support to legal team pursuing claims against owner
  • Assisted in preparation of expert report

Northport Power Plant, Long Island, NY

  • Renovation of existing, operating power plant
  • Analyzed contractor’s delay and disruption claims
  • Identified key documents supporting contractor claims and prepared exhibits and demonstrative graphics
  • Provided litigation support to legal team pursuing claims against owner
  • Assisted in preparation of expert report

St. John the Baptist Parish Treatment and Lift Station, New Orleans, LA

  • Performed default evaluation and takeover negotiations for surety
  • Responsible for project re-lets and site monitoring through owner acceptance of all defaulted projects
  • Monitored system start-up and project close-out
  • Negotiated change orders and claims with Parish on behalf of surety

Coastline Convention Center, Wilmington, NC

  • $3,000,000 renovation of riverfront warehouse
  • Developed CPM schedule and monthly updates on behalf of contractor
  • Prepared change orders and time extension requests
  • Developed and maintained cost forecasting system tied to progress
  • Negotiated change orders and time extensions